HCC Contracting completes the erection of over 50 tilt-wall panels on the 360 Commerce Project

HCC Contracting completes the erection of over 50 tilt-wall panels on the 360 Commerce Project.
The combined weight of the 9-1/4” panels was 4,250,000 pounds. This phase of the project was done with no injuries!

By commercialcontractinghcctx

Bob L. Blackwelder / Principal Experience & Current Responsibilities: Complete buy out schedule, Sub Contract Procurement, Coordinate with all owners consultants preparing all General Provisions, Special Provisions and Division One documents. Including baseline schedule in Microsoft Project format, manpower loaded and resource loaded. Three week outlook schedule. Assemble and maintain all RFI, RFP, MSDS and Submittal logs. Prepare and submit for approval G-702 & 703 for application for payments, all release of liens for both contractors and suppliers. QC program, weekly progress meeting minutes for owners.